Friday, January 30, 2009
Roof Framing Nears Finish

Thursday, January 29, 2009
Crews Resume Work @ Burger King

Finally, we were able to return to work today. The demo, framing, and coverup of the playplace was started. The crews got about half of it done. The rest will be done tomorrow. All subcontractors were onsite today for a preconstruction meeting with Cliff and Woody. Also, on site today was John Kostel, owner. This pic shows the demo work, followed by framing, and finally the cover up. Best of all, you can see we had clear blue skies.
Wednesday, January 28, 2009
Frozen Pipes, Icy Sidewalks, Cold Tempertures

Tuesday, January 27, 2009
Rain Delays Progress at Paris' Burger King
Cold, breezy, rainy! That is what today was like. Later in the evening you could here the rain had turned to falling ice. The work scheduled for today was all outside work. It had to be postponed due to it being too cold and wet.
Tomorrow will probably not be any better. The positive thing in this is that the crews are far enough ahead of schedule that a couple of down days won't delay the overall job.