Current Project is Olive Garden in Amarillo, TX
For a larger view of a photo, click directly on the photo.
Olive Garden
Saturday, February 28, 2009
Remodeling the Home of the Whopper....
Friday, February 27, 2009
Burger King Wall & Floor Finishes Starts Today
Burger King Roof Top View
Thursday, February 26, 2009
EIFS Work Complete at Burger King
Wednesday, February 25, 2009
Burger King's Drive Thru Demolition Continues
Tuesday, February 24, 2009
Remodeling Project @ Burger King in Paris, TX
What stood out the most was the sheetmetal paraphet caps the roofing crew installed today. Added another color to the exterior.The drywall crew is just about finished will all FRP & they did finish the sheetrock.
The electricians are finally pulling new wire.
The stone crew was applying stone on the drive thru side of the building.
The EIFS crew has done all EIFS at the trash enclosure, except the color. Color application is scheduled for tomorrow. Also, at the trash enclosure, the gate frame was put in place and the door gates were then finished.
Monday, February 23, 2009
Burger King Sign
Sunday, February 22, 2009
Overview: Home of the Whopper!
Saturday, February 21, 2009
Saturday: Drywall Crew continues @ Burger King
Friday, February 20, 2009
MEP's Work at record setting speeds....
Well, maybe, they aren't setting records, but they continue to meet or beat the schedule. I've mentioned in previous entries that the quality of subcontractor determines the not only the quality of the project, but also the ability to understand the time is of the essence. These crews on the Burger King project taking their work seriously. The EIFS work on the main building is complete. The crew moved out to work on the trash enclosure. A separate crew is working on stone application. After installing the broiler hood, the HVAC crew worked on the broiler vent pipe. The electricians & plumbers finished their roughing in and are ready for inspection on Monday. Lastly, the drywall crew worked on the sheetrock and FRP applications. The drywall and EIFS crews are scheduled to work this weekend. HVAC crew passed their City inspection, so lines are ready to wrap. John Kostel came out again today. Woody and he were able to review all issues requiring the owners attention. It was definitely a great work week.
Thursday, February 19, 2009
Exterior & Interior Work Progresses
A crew worked on the EIFS on the drive thru side of building. Then later continued with stone application on front of building. The new trunk lines were installed over the front counter. The electricians and plumbers are doing their roughing in work. Another crew stayed busy tape and bedding in the lobby.
Wednesday, February 18, 2009
Burger King Interior & Exterior Progress
Tuesday, February 17, 2009
Burger King: New look coming up
veneer application. It was going to start yesterday, but rain was in the forecast. Today it is sprinkling off and on, but they were able to start. Clear skies are scheduled tomorrow. This work will probably be complete by the end of the week. The EIFS crew also returned to continue their work in the drive thru.
Monday, February 16, 2009
BURGER KING: Concrete Poured
Saturday, February 14, 2009
Valentine's Day at Burger King
Friday, February 13, 2009
End of Another Week @ Burger King
Thursday, February 12, 2009
Burger King Remodel Progresses
Wednesday, February 11, 2009
Burger King: Interior Progress
Tuesday, February 10, 2009
DECONSTRUCTION of Kitchen Nears End
Monday, February 9, 2009
Demo Continues Inside Despite the Rain
The first rain spell came in at 4am. It didn't last long. But about 6am it was coming down again. It was not any thing more than rain and a small breeze. But it was enough to have to call off all scheduled exterior work. The interior work, however, continued as planned. The most interesting photos of today are these below. In the top section, we see the demo crew has been assigned with the task of moving a safe that has not been moved in many, many years. (Someone thinks it could be as much as 30 years. We don't actually know how long it has been there. ) The photo indicates three men working on the project. It looks like a push and pull job. The photo beneath those is one of a "de-struction" man removing tiles and a "con-struction" plumber.
Saturday, February 7, 2009
Progress of Exterior Work @ Burger King
The subcontractor doing the exterior finishing work, had a crew on site over the weekend. They were able to make visible progress. Some of the color has already been added. These photos show various stages of this work as it's in progress.
Hopefully, the rain forcasted for the coming week won't linger and allow work to continue on the exterior of the building.