Current Project is Olive Garden in Amarillo, TX
For a larger view of a photo, click directly on the photo.
Olive Garden
Monday, August 24, 2009
Pictures Are Good, Video Is Better
Friday, August 21, 2009
Day Six, Friday
Richard & Woody are working through the weekend continuing the split shift of the 24/7 in order to meet their deadline. The progress over the past days has been remarkable. The quality of the work is also great. Richard was able to find another crew of trim carpenters to come in and continue when the first crew finished the first shift. This allows them to have trim carpenters around the clock. During the day the millwork company delivered more wood trim. All MEP crews worked today.
Thursday, August 20, 2009
Day Five, Thursday
The morning started with the glass subcontractor needing confirmation of window sizes. Plumbing & Electrical inspections are called in for Wednesday. So project new end date is listed as the 27th now. Millwork arrived in the afternoon as did the roll off for all debris. Plumbers installed all water lines at bar & turned water back on. They also did the top out plumbing work. Concrete was poured & finished in the bar. Electricians worked on installing outlets and fans. Framers finshed frame work on bar drop down. Trim carpenters did trim work at glass & booth walls. Meanwhile the mechanics worked on A/C drops. BUSY BUSY BUSY.....That's Progress.
Wednesday, August 19, 2009
Day Four
Framed ceiling over bar, applied sheetrock at bar & glass wall. Electricians added electrical boxes & lights in bar ceiling. Painters continued stain work & did first coat of mud at soffit. Plumbers came in to repair a water line at the bar. Trim work was continued by trim carpenters at glass wall and bar. Also, the tile crew set bar tile & put down floor leveler. Plumbing & Electrical inspections passed today. FRP work behind bar is complete. As for Richard & Woody, they are hanging on for the ride. It's going at a fast pace and it's hold on or get left behind. Those two aren't getting left behind.
Tuesday, August 18, 2009
Day Three
Richard Grigsby & Woody Gibson are really into the swing of it at the Black Finn in Arlington. They continue to split the 24/7 shift between the two of them. To meet their goals, both of these Supers know they will be working long hours, catching 4 or 5 hours sleep in between and get back to it. The quality of the work in excellent as is the progress. Trim Carpenters working on "glass" wall, bar, & end walls @ platform. Meanwhile, painters tape & bed, plus do some stain work.
Saturday, August 15, 2009
Birthday Lady
Friday, August 7, 2009
Project Excellence Awarded