Olive Garden

Tuesday, March 25, 2008

North Parking Lot & Framing Complete!

Framers finished up tonight and will return after the inspection to Tyvek. Meanwhile, the concrete crew came in today and poured the north parking lot. The plumbers continued their work on the roof drains. The surveyors were here to start laying out the south and west side curbs. The mechanical crew came in to do some preliminary work and will begin the hvac trunk line tomorrow.