The electricians worked on overhead conduits while the framing crew started wrapping the building in Tyvek. The glass crew continued to frame windows. The city passed us on the framing inspection. Over all the work is progressing on schedule. Most of the delays are electrical is having to catch up to the schedule due to days they didn't show. Next is the concrete crew fell behind schedule waiting for the electricians. Both crews should be onsite next week making up lost days. OSHA came by for an inspection. Aside from having to stop all work while the inspection is in progress, work was able to continue after the inspection. The crew started insulating the unit and they were able to permanently secure the ladder inside to access the roof.