Current Project is Olive Garden in Amarillo, TX

For a larger view of a photo, click directly on the photo.

Olive Garden

Tuesday, May 13, 2008

McDonald's Deadline 9 Days Away

Wallpaper hanging was completed today as was the stone work on the building. The tile crew is close to finishing. The electricians connected kitchen equipment as the installers set it up. Add to the mix the decor crew that arrived to put on all those finishing touches. The plumbers are working in the restrooms and other finishing touches. The landscapers are scheduled for Thursday and final concrete work is scheduled for Friday and Saturday. Ceiling tile will be completed when kitchen installers and decor are finished in the building. EXCELLENT!

THANK YOU FOR BROWSING OUR PAGE