We've scheduled delivery of the generator for tomorrow. Also, we'll have the drilling for the piers going on tomorrow and in the afternoon the piers will be poured. To make this happen the excavators will have to have the pad ready and lab will need to give the thumbs up on compaction. So today it's a matter of continuing the dirt work. Woody met with the Cross Rep regarding the lot lighting. Concrete company had men onsite today tying steel for the piers. The highlight of the day was having Michael Sawyers visit the site. He reviewed plan changes and scheduling with us. This picture shows how much dirt has been cut out of the lot to bring it to grade. This should allow you to see why we have spent so many days on exporting dirt.