Grading is scheduled to be completed by the end of this week. Meanwhile, we will begin drilling the piers today. That meant the GEO Tech company was onsite to conduct inspections throughout the process. Furthermore, we had a City Building Inspector come out to do the city inspection for piers and cages. Woody has started scheduling work for next week. We'll lose a work day right at the beginning of the month with the Labor Day holiday. Our goal is to be able to meet our scheduled weekly deadlines in the four day work week, all the same.