Today is the 6th day we've lost due to the temporary hold on the project. The questions Woody raised on the 6th of August regarding the depth of the cuts were taken seriously by our Project Manager and the McDonald's Area Construction Manager. It caused the job to be placed on hold while an investigation was started. The engineering company and developer were brought in to shed light on the situation. Finally, today we held a meeting regarding the conflict in the topo numbers. Ben Sims came from the engineering company and Dan Dover and Reese were present to represent the developer. After the meeting we were given permission to continue with the grading per plan. Woody scheduled the grading company and their surveyors to return tomorrow to continue grading the lot.