Today the grading crew continued to grade the site & 4 trucks were used continuously throughout the day to haul out the dirt. The concrete crew came in to start constructing the pier cages to be used next week when we begin drilling the piers. We had to move the job trailer and portolet to allow the developers electrician to relocate their electrical line. Woody continues to be uneasy about the depth of the cuts made on the site. Jimmy Lopez, McD Area Construction Manager, came out to get a visual of Woody's concerns. Concerns will be addressed at tomorrow's weekly site meeting. For now Woody is progressing per plan.