Current Project is Olive Garden in Amarillo, TX

For a larger view of a photo, click directly on the photo.

Olive Garden

Saturday, August 23, 2008

Rained Out Aug 15th to Aug 23rd

Last Friday, we changed the location site for our weekly site meeting. We discussed the delay due to grading issues and rain days with the McDonald's Partner. Discussions continued regarding decor, kitchen equipment, exterior wall coverings and colors, etc. Woody showed Mr Jasper and Michael Sawyers the changed grading plan that Ben Sims provided him yesterday. We've sent the changes to the grading company. On Thursday, although the site was too wet to work, the concrete crew came out and began pumping water off the building pad. We're hoping to return to work on Monday. The sun has been in and out over the weekend drying the ground some.