Current Project is Olive Garden in Amarillo, TX

For a larger view of a photo, click directly on the photo.

Olive Garden

Monday, October 29, 2007

Busy Monday....


All door glass arrived today. The carpenters installed all door glass. Patio sliding doors were completed today.

Health inspection at 10:30am. We received a TCO and they will return Mon, Nov 5 for final health dept inspection. Health Dept is permitting training and stocking of dry goods. Perishables can be delivered Monday, Nov 5th.

Painters are finishing all touch ups. Carpenters are installing the round booths.

Turn over has been postponed to Nov 5th.