The morning started with the glass subcontractor needing confirmation of window sizes. Plumbing & Electrical inspections are called in for Wednesday. So project new end date is listed as the 27th now. Millwork arrived in the afternoon as did the roll off for all debris. Plumbers installed all water lines at bar & turned water back on. They also did the top out plumbing work. Concrete was poured & finished in the bar. Electricians worked on installing outlets and fans. Framers finshed frame work on bar drop down. Trim carpenters did trim work at glass & booth walls. Meanwhile the mechanics worked on A/C drops. BUSY BUSY BUSY.....That's Progress.