Current Project is Olive Garden in Amarillo, TX

For a larger view of a photo, click directly on the photo.

Olive Garden

Friday, October 9, 2009

First Week at Brio Complete



  • Concrete crew saw cutting at bar area to include the area for the electrical conduit
  • Plumbers running soda line from bar to the back of building
  • Went on upper floors found NO access to grease duct shaft
  • Received plumbing & framing materials
  • Received POs for portolet & roll off
  • Rained off and on through out the day