From Brio Pix |
You will need to turn down the sound as the equipment noise is very loud. The concrete sawcutting work is progressing. This includes the removal of the concrete debris. We are running on schedule. It is a very hot and humid day today. The electricians are working on getting us some temporary power. The plumber stopped by to check out the site. Plumbing crew will start in the morning. Brio Project Manager visited the job site today. He was checking to see if we were able to start and inspected progress made so far.