Monday came and went too fast. The glass crew and framing crew arrived to start the work on the exterior of the play place. The glass is to be removed. Then the top and outside ends will beframed. This will be filled in with EIFS at the end of the week. On this first side, the east side the decision was made to remove all the glass to avoid the glass breaking while the frame goes in on the top row.
The photos show the progression of this work.
Tomorrow the owner and Project Manager will be meeting on site to finalize scheduling.
The crews made good progress today.