Current Project is Olive Garden in Amarillo, TX

For a larger view of a photo, click directly on the photo.

Olive Garden

Monday, October 20, 2008

Inspections Pass at McDonald's

Concrete crew continues to form the NE central section to be poured tomorrow. The utility contractor was approved by the Fire Marshall to cover up. Hydrostatic and fire & sprinkler inspection to be held next week. The framers finished insulating walls and continued to cover walls. Sprinkler crew continued to run lines. The electricians were only able to work two hours today. The brick masons continued on the back corner. Stone masons prepared for inspection tomorrow. The city of Fort Worth passed the HVAC and insulation inspection. The roofing crew should return next week to put the metal on the roof.