Today the exterior work continued with the start of the stoneveneer application. It was going to start yesterday, but rain was in the f
orecast. Today it is sprinkling off and on, but they were able to start. Clear skies are scheduled tomorrow. This work will probably be complete by the end of the week. The EIFS crew also returned to continue their work in the drive thru.Inside the concrete crew returned to finish up the kitchen concrete work. Also working inside were the electricians as they began pulling wire.