The concrete crew came out today and started the demolition of the concrete under the drive thru window where the grease trap is located. The grease trap will be replaced and relocated.
What stood out the most was the sheetmetal paraphet caps the roofing crew installed today. Added another color to the exterior.The drywall crew is just about finished will all FRP & they did finish the sheetrock.
The electricians are finally pulling new wire.
The stone crew was applying stone on the drive thru side of the building.
The EIFS crew has done all EIFS at the trash enclosure, except the color. Color application is scheduled for tomorrow. Also, at the trash enclosure, the gate frame was put in place and the door gates were then finished.