The demo of the kitchen floor, wall, and ceiling tiles continued. The EIFS work continued outside on the drive thru side. The ceiling tiles were delivered and stored. Burger King reps continued to work on the removal of the pos system. The mechanical techs removed the old a/c unit and fans. The sanitation company had to come switch out the 40 yard container again. This is the second time since the demo work started. Overall, the day went well and progress is on schedule. The EIFS work will continue over the weekend. As of now the plans are laid out for the coming week, but the forcast is still calling for rain through the middle of next week. We will have to see how it goes.