Today the sign on the building was put in place by the electricians. It's always interesting to see the crews do this. After this the electricians worked in the kitchen. John Kostel came by and met with the HVAC foreman regarding the stainless steel to be installed. All measurements were taken. The drywall crew continued with sheetrock and FRP installation. Woody has also made arrangements to have the tile crew arrive on Thursday to begin work. After today we are down to 30 days to meet our goal.