A crew worked on the EIFS on the drive thru side of building. Then later continued with stone application on front of building. The new trunk lines were installed over the front counter. The electricians and plumbers are doing their roughing in work. Another crew stayed busy tape and bedding in the lobby.
John Kostel came by today. We met with the corian installer. This allowed us time to coordinate and confirm colors to be used. The corian will not be changed from plans. The City of Paris Inspector came by for a framing inspection. He has now permitted crews to cover the old walls with sheetrock or FRP.
These photos reflect the work being completed both inside and out.